Keep Us Strong WikiLeaks logo

Currently released so far... 5422 / 251,287

Articles

Browse latest releases

Browse by creation date

Browse by origin

A B C D F G H I J K L M N O P Q R S T U V W Y Z

Browse by tag

A B C D E F G H I J K L M N O P Q R S T U V W X Y Z
QA
YM YI YE

Browse by classification

Community resources

courage is contagious

Viewing cable 07SANJOSE426, COSTA RICAN TELECOM UPGRADE ON TRACK

If you are new to these pages, please read an introduction on the structure of a cable as well as how to discuss them with others. See also the FAQs

Understanding cables
Every cable message consists of three parts:
  • The top box shows each cables unique reference number, when and by whom it originally was sent, and what its initial classification was.
  • The middle box contains the header information that is associated with the cable. It includes information about the receiver(s) as well as a general subject.
  • The bottom box presents the body of the cable. The opening can contain a more specific subject, references to other cables (browse by origin to find them) or additional comment. This is followed by the main contents of the cable: a summary, a collection of specific topics and a comment section.
To understand the justification used for the classification of each cable, please use this WikiSource article as reference.

Discussing cables
If you find meaningful or important information in a cable, please link directly to its unique reference number. Linking to a specific paragraph in the body of a cable is also possible by copying the appropriate link (to be found at theparagraph symbol). Please mark messages for social networking services like Twitter with the hash tags #cablegate and a hash containing the reference ID e.g. #07SANJOSE426.
Reference ID Created Released Classification Origin
07SANJOSE426 2007-03-05 20:08 2011-03-03 16:04 UNCLASSIFIED Embassy San Jose
Appears in these articles:
http://www.nacion.com/2011-03-03/Investigacion/NotasDestacadas/Investigacion2697430.aspx
http://www.nacion.com/2011-03-03/Investigacion/NotaPrincipal/Investigacion2697496.aspx
http://www.nacion.com/2011-03-03/Investigacion/NotasSecundarias/Investigacion2697489.aspx
http://www.nacion.com/2011-03-03/Investigacion/NotasSecundarias/Investigacion2697532.aspx
http://www.nacion.com/2011-03-03/Investigacion/NotasSecundarias/Investigacion2697535.aspx
http://www.nacion.com/2011-03-03/Investigacion/NotasSecundarias/Investigacion2701964.aspx
http://www.nacion.com/2011-03-03/Investigacion/Relacionados/Investigacion2701965.aspx
VZCZCXYZ0029
RR RUEHWEB

DE RUEHSJ #0426 0642018
ZNR UUUUU ZZH
R 052018Z MAR 07
FM AMEMBASSY SAN JOSE
TO RUEHC/SECSTATE WASHDC 7411
INFO RUEHZA/WHA CENTRAL AMERICAN COLLECTIVE
UNCLAS SAN JOSE 000426 
 
SIPDIS 
 
SIPDIS 
 
E.O. 12958: N/A 
TAGS: ETRDEINVTINTCS
SUBJECT: COSTA RICAN TELECOM UPGRADE ON TRACK 
 
1.  Summary.  Costa Rica's parastatal telecom monopoly, Instituto 
Costarricense de Electricidad (ICE), announced plans to invest 
US$59.8 million for installation of a nationwide fiber optics 
network upgrade to improve its broadband internet capacity and 
coverage.  This investment is being made so ICE can better compete 
under CAFTA.  End Summary 
 
2. ICE signed an agreement with ECI Telecom, an Israeli network 
provider, in October 2005, which just gained final contract approval 
from the GOCR comptroller's office.  Utilizing ECI's design, ICE has 
already completed up to 40% of the network which will comprise a 
total of five separate rings covering border to border and sea to 
sea creating improved international interconnection for its network. 
 The backbone network will provide ICE with additional capacity to 
deliver voice and data services to fixed and mobile subscribers. 
The project completion date is set for mid 2008. 
 
3.  The project includes the delivery and installation of ECI's XDM 
converged SDH and DWDM optical platforms, which enable up to 40 
channels and 10 Gigabits each, meeting the long-term bandwidth 
capacity needs of ICE.  In addition, the project will give ICE an 
advanced network architecture for future services and expansion to 
meet the needs of both residential and business communities. 
 
4.  Under the terms of the contract, ECI Telecom has provided all 
aspects of the network design and installation for over 1,000 km 
across urban and rural areas of Costa Rica.  The total project cost 
is $US59.8 million.  ICE will contribute US$28.6 million and the 
Central American Bank for Economic Integration will provide a loan 
for the remaining US$32.5 million. 
 
5.  Most industry observers think ICE would not be making this kind 
of investment without the competitive environment created by CAFTA 
looming on the horizon.  In that sense CAFTA is already spurring 
investment that will benefit Costa Rican telecom consumers. 
WEITZENKORN